Field operations
How many work orders will remain at our current completion rate?
Add expected arrivals over the horizon to the starting queue. Complete up to the available weekly slots, capped at total orders. Assume each week’s arrivals are available for booking that week and each order uses one slot.
Use the free calculator Get the business edition · €29
Worked example
With the example inputs below, the calculator returns these results.
Orders still open at end 16
- Open orders at start
- 32 orders
- New orders per week
- 16 orders
- Completion slots per week
- 20 orders
- Planning horizon
- 4 weeks
Other results
- Orders completed
- 80
- Total orders in period
- 96
Use your own figures
Check whether current staffing can clear the queue over the next few weeks. Open the worksheet, replace the example values, then copy or print the result.
Service backlog projection →