How long should the floor stay closed while we apply the finish?
Application hours equal area times coats divided by team rate. Add one specified wait between coats and one final wait after the last coat. Enter the product and site-specific waiting times for the intended use.
Use the free calculator Get the business edition · €29
Worked example
With the example inputs below, the calculator returns these results.
Planned closure 6.75 h
- Floor area
- 120 m²
- Team application rate
- 60 m²/h
- Coats to apply
- 2 coats
- Wait between completed coats
- 45 min
- Wait after final coat
- 120 min
Other results
- Application time
- 4 h
- Waiting time
- 2.75 h
Use your own figures
Give the site contact a reopening estimate that includes the final wait. Open the worksheet, replace the example values, then copy or print the result.
Floor finish closure window →