How long should the floor stay closed while we apply the finish?

Application hours equal area times coats divided by team rate. Add one specified wait between coats and one final wait after the last coat. Enter the product and site-specific waiting times for the intended use.

Use the free calculator Get the business edition · €29

Worked example

With the example inputs below, the calculator returns these results.

Planned closure 6.75 h

Floor area
120 m²
Team application rate
60 m²/h
Coats to apply
2 coats
Wait between completed coats
45 min
Wait after final coat
120 min

Other results

Application time
4 h
Waiting time
2.75 h

Use your own figures

Give the site contact a reopening estimate that includes the final wait. Open the worksheet, replace the example values, then copy or print the result.

Floor finish closure window →