Can my crew reach the next site before the arrival deadline?
Sum remaining work, travel and entry minutes from now. Compare this duration with the minutes until the latest acceptable arrival. Early arrival produces spare time and a missed deadline produces lateness.
Use the free calculator Get the business edition · €29
Worked example
With the example inputs below, the calculator returns these results.
Projected lateness 0 min
- Time until latest acceptable arrival
- 85 min
- Work left at current site
- 30 min
- Drive to next site
- 35 min
- Parking and site entry
- 10 min
Other results
- Spare time before deadline
- 10 min
- Time from now to arrival
- 75 min
Use your own figures
Give dispatch an early estimate of lateness or spare time. Open the worksheet, replace the example values, then copy or print the result.
Next appointment arrival check →